Arrow-right Camera
The Spokesman-Review Newspaper
Spokane, Washington  Est. May 19, 1883

Tribe files legal challenge to stall Dakota Access pipeline

Opponents of the Dakota Access pipeline join protestors around the country, in response to the Army Corps of Engineers saying it will clear the way for completion of the disputed $3.8 billion project to carry North Dakota oil to Illinois, outside the Army's offices in Los Angeles Wednesday, Feb. 8, 2017. Dallas-based Energy Transfer Partners, on Wednesday got final permission from the Army to proceed with a crossing of the Missouri River in southern North Dakota. The tribe fears a pipeline leak could contaminate its drinking water. (Damian Dovarganes / AP)
By James Macpherson and Blake Nicholson Associated Press

CANNON BALL, N.D. – Construction of the Dakota Access pipeline under a North Dakota reservoir has begun and the full pipeline should be operational within three months, the developer of the long-delayed project said Thursday, even as an American Indian tribe filed a legal challenge to block the work and protect its water supply.

The Army granted Energy Transfer Partners formal permission Wednesday to lay pipe under Lake Oahe, clearing the way for completion of the 1,200-mile, $3.8 billion pipeline. ETP spokeswoman Vicki Granado confirmed early Thursday that construction resumed “immediately after receiving the easement.”

Workers had already drilled entry and exit holes for the crossing, and oil had been put in the pipeline leading up to the lake in anticipation of finishing the project.

“The estimate is 60 days to complete the drill and another 23 days to fill the line to Patoka,” Granado said, referring to the shipping point in Illinois that is the pipeline’s destination.

Work was stalled for months due to opposition by the Standing Rock Sioux and Cheyenne River Sioux, as well as a prolonged court battle between the developer and the Army Corps of Engineers that oversees the federal land where the last segment of the pipeline is now being laid. President Donald Trump last month instructed the Corps to advance pipeline construction.

The Cheyenne River Sioux on Thursday asked a federal judge to stop the Lake Oahe work while a lawsuit filed earlier by the two tribes against the pipeline proceeds. Attorney Nicole Ducheneaux said in court documents that the pipeline “will desecrate the waters upon which Cheyenne River Sioux tribal members rely.”

ETP, which maintains the pipeline is safe, didn’t immediately respond in court to the filing. U.S. District Judge James Boasberg didn’t immediately rule.

The tribes’ lawsuit filed last summer maintains that the pipeline project threatens their water and cultural sites. It’s been on hold while the river crossing dispute has played out. The Cheyenne River Sioux on Thursday told Boasberg that it also wants to make a claim on freedom-of-religion grounds.

“The sanctity of these waters is a central tenet of their religion and the placement of the pipeline itself, apart from any rupture and oil spill, is a desecration of these waters,” Ducheneaux wrote.

Standing Rock Sioux attorney Jan Hasselman has said that tribe will also try to block the lake crossing in court, with likely arguments that further study is necessary to preserve tribal treaty rights and that it’s part of the legal process for the company to obtain final permission to finish the pipeline.

An assessment conducted last year determined the river crossing would not have a significant effect on the environment. However, the Army decided in December that further study was warranted to address tribal concerns.

The Corps launched an environmental impact study on Jan. 18, but Trump signed an executive action six days later telling the Corps to allow the company to proceed with construction. Legal experts have disagreed on whether the Army can arbitrarily change its mind because of the change in White House administrations.

An encampment near the construction site has drawn thousands of protesters since April in support of the tribes, leading to occasional clashes with law enforcement and hundreds of arrests.

Granado said she was not aware of any incidents involving pipeline opponents in the area Thursday. The Morton County Sheriff’s Office also said it had not responded to any incidents.

Standing Rock Sioux Chairman Dave Archambault said in a statement late Wednesday that the tribe is prepared to keep up the battle in the courts, “to fight against an administration that seeks to dismiss not only our treaty rights and status as sovereign nations, but the safe drinking water of millions of Americans.”

In a statement Wednesday, North Dakota Gov. Doug Burgum urged “cooperation and restraint” from all parties and requested federal law enforcement assistance to keep the peace during construction.

Protesters rallied in several U.S. cities Wednesday. Joye Braun and Payu Harris, two pipeline opponents who have been at the North Dakota protest encampment, said in an interview at a nearby casino that there’s frustration but also resolve in the wake of the Army’s decision.

“The goal is still prayerful, nonviolent direct action,” Braun said.