Arrow-right Camera
The Spokesman-Review Newspaper
Spokane, Washington  Est. May 19, 1883

23 years later, Hanford site set to treat WWII, Cold War radioactive waste

Tanks that are part of a cesium removal system in March 2023 at the Hanford Nuclear Reservation, a site that was integral to the nation’s nuclear arsenal after World War II.  (New York Times)
By Annette Cary Tri-City Herald

RICHLAND – More than two decades after construction of the Hanford nuclear site’s massive vitrification plant began, the plant has taken one of the final steps to begin treating waste for disposal as soon as this summer.

Bechtel National workers have begun operating the plant using chemicals that simulate the radioactive and hazardous chemical waste that will be treated there.

The plant will initially turn some of the least radioactive waste stored in underground tanks for as long as 81 years into a stable glass form.

“Beginning nitrate feed is the next crucial step in starting environmental testing of the Low-Activity Waste Facility and ensuring operations are protective of human health and the environment,” said Suzanne Dahl, the tank waste treatment section manager of the Washington state Department of Ecology’s Nuclear Waste Program.

The vitrification plant’s new operators have been practicing making glass at the Low Activity Waste Facility since the first container was filled with glass at the end of 2023.

Now Department of Energy contractor Bechtel National has begun making glass that incorporates nonradioactive chemicals to simulate turning radioactive waste into a stable glass form for disposal.

Ammonia and nitrous oxide-producing chemicals are being added to plant’s melters along with glass forming material that is heated to 2,100 degrees Fahrenheit. The molten mixture will then be poured into stainless-steel containers for disposal at a lined landfill at Hanford after cooling.

The current step of turning the waste simulant into a stable glass form tests the glass-making system and its components, including demonstrating that its exhaust system works as designed to filter off-gases released through its stack to meet strict environmental regulations.

The plant will next need to pass a Washington state Department of Ecology environmental performance demonstration and then a DOE operational readiness review.

If work proceeds as planned, Bechtel National then could start making glass that incorporates radioactive waste as soon as late July and have a full 4-feet-wide by 7.5-feet-tall canister of glassified waste in August.

New Hanford site contractor

That will be 23 years after ground was broken to build the Hanford Waste Treatment Plant, commonly called the vitrification plant.

Progress to start treating radioactive waste “is the result of decades of preparation, dedication and collaboration between the department and our contractor partners and is another step toward safely addressing Hanford tank waste,” said Brian Harkins, acting DOE manager of Hanford.

The waste is left from chemically processing uranium fuel irradiated in Hanford reactors to produce nearly two-thirds of the plutonium for the nation’s nuclear waste from World War II through the Cold War.

The work left 56 million gallons of a mix of radioactive and hazardous chemical waste stored in underground tanks, some of them prone to leaking, until the waste could be treated for disposal.

The Low Activity Waste Facility will have two 300-ton melters for heating up the waste mixture, making them the largest waste glass melters in the world, at three times or more larger than any others in the world, including those used in France, England and at DOE’s Savannah River, South Carolina, site.

Once the first radioactive waste is glassified at the vitrification plant in the step called hot commissioning, Bechtel National will continue treating radioactive waste for six to 18 months before the work transitions to the new Hanford tank waste contractor, said Mat Irwin, the DOE assistant manager for the vitrification plant at the May meeting of the Hanford Advisory Board.

Hanford Tank Waste Operations and Closure, or H2C as it is called at Hanford, was awarded the contract to manage radioactive tank waste and also to become the first operator of the vit plant to treat low-level radioactive waste at the vit plant once commissioning is completed.

H2C – a joint venture of BWX Technologies, Amentum and Fluor – in February completed a four-month transition period with the outgoing contractor to manage the Hanford waste storage tank farms and then take over vitrification plant operations for low activity waste treatment.

DOE will pick the right time for H2C to start the transition for vitrification plant operations from Bechtel National, based on what tank projects H2C is working on and unrelated activities at the vitrification plant to prepare for treating the most radioactive waste, Irwin said.

The High Level Waste Facility is still under construction at the vitrification plant to treat the most radioactive waste in Hanford’s underground storage tanks. A federal court consent decree requires that treatment to begin in 2033.

Vit plant safety issue addressed

Starting to operate the plant with the waste simulant is a testament to the teamwork and technical expertise of those working on the project, said Brian Hartman, Bechtel National project director.

“Leadership from DOE and strong partnerships with the trade unions, suppliers, regulators, other Hanford contractors, and local community have helped make this happen,” he said.

One of the last hurdles DOE had to clear to begin operating the plant with simulated waste was an unexpected need to inspect and repair the ammonia system for the low-activity waste treatment portion of the plant.

The plant has two tanks, each approximately 24 feet long and 7 feet in diameter, with a capacity of 6,000 gallons of liquid ammonia each.

Degraded gaskets were replaced and the valves were rebuilt in the ammonia system.

There were two incidents when workers were told to take cover indoors after ammonia was added to the system and leaks were detected.

The first take cover order was in December for part of central Hanford and the second take-cover incident was in the spring and was for workers only on the 65-acre vitrification plant site.

When the vitrification plant is treating waste, it will release oxides of nitrogen into the Low Activity Waste Facility’s exhaust system.

Ammonia will be used to cause a chemical reaction that significantly reduces the level of oxides of nitrogen to meet air permit levels.