From LCSC spokesman Keith Erickson: Paving of the new East Lot near City Hall and the reconstructed lot in the same area will begin next Thursday. Work will take about three days, officials said Wednesday morning during a weekly McEuen project update. Base rock will be put down today and tomorrow. Construction will ultimately increase parking in the City Hall vicinity from 65 spaces to 187 and offer 23 boat trailer parking spaces. Meantime, there will temporary delays to traffic at 8th Street and Bancroft Avenue Thursday while crews perform asphalt patch work. Work continues on schedule, engineer Phil Boyd said Wednesday.