Public Can Watch McEuen Field Work
From City Clerk Renata McLeod’s draft minutes of City Council meeting Tuesday:
Dennis Grant, Engineering Project Manager, informed the City Council that the 2012 McEuen project (on the south side of City Hall) has entered the landscaping phase with the paving of the trail to be next. The 2013 McEuen project is currently in the mass grading and shoring phase. The trail outside the fencing is a good location for citizens to witness the construction activities. Currently the contractor is installing stormwater facilities from the splash pad to the harbor house and is about 50% complete. The Osprey are back and are nesting on the middle pole. The contractor is beginning to do the footings of the parking structure and elevators. Complete draft minutes here.
Question: Do you plan to use the new trail along Tubbs Hill to watch McEuen Field construction work?
* This story was originally published as a post from the blog "Huckleberries Online." Read all stories from this blog