Park road repair set back
LONGMIRE, Wash. – Recent snow and rain has slowed repairs to the most traveled road in Mount Rainier National Park, delaying the return of public access to Paradise and Longmire.
“What we have been saying all along is if everything went perfectly, we would be open by mid-March,” park spokesman Kevin Bacher said Friday. “At this point, it will be early April.”
Most of the park has been closed since Nov. 6 after 18 inches of rain fell in 36 hours.
Working to get Nisqually Road open, park road crews and maintenance workers have endured days of cold, rain and snow.
“I’ve lost count of how many days I’ve worked since this started in November,” said Cody Manzer, a heavy equipment operator for the park. “I did work 17 days in a row at one point.”
With most of the park’s other damaged roads under snow, crews have focused on repairing Nisqually Road.
On Thursday, crews began installing the first of two sets of culverts to manage Kautz Creek about three miles from the Nisqually entrance.
Debris created by the November floods forced the creek out of its channel and through the forest. Since then it’s been flowing over the road.
Three culverts, 30 inches wide by 40 feet long, will be installed about a quarter-mile from the existing Kautz Creek bridge. Crews will then redirect the creek under the road by installing two 12-foot-wide culverts.
“They are intended to withstand a 50-year flood,” Bacher said.
It could take most of the summer to repair large washouts at other roads such as state Route 123, and Stevens Canyon and Carbon River roads, Bacher said.
At milepost 5 on Nisqually Road, crews have started repairing a 65-foot slide and eventually plan to rebuild the embankment.
“In order to put that in place, we have to build a temporary access road along the river.” Bacher said. “This past week, our crews have been cutting that road so they can deliver the materials to build that.”
The National Park Service and the Federal Highway Administration have provided $36 million for work at Kautz Creek and on other park roads. Earlier this month, U.S. Rep. Norm Dicks announced that $18 million from unspent highway and construction accounts would go toward repairing damage in the park.