McEuen: Paving Set For City Hall Lots
Keith Erickson, spokesman for Lake City Development Corp, provides latest developments of McEuen Field upgrade:
Base rock is being placed on the two new parking lots near City Hall with paving expected later this week, weather permitting, according to Team McEuen engineer Phil Boyd. Additionally, crews are constructing a new 60-foot retaining wall on Young Avenue near City Hall that could cause minor traffic delays during the early part of the week. The McEuen project continues on schedule. Meantime, city crews are replacing leaky water valves near Sherman and First Street and Sherman and Second Street, which will require road closures/detours on Tuesday.
Also: LCDC minutes from October 2012 meeting